2021 Street & Utility Improvements

As part of the City’s continuing public improvement efforts in 2021, the City has authorized its consulting engineer, Bolton & Menk, to prepare a feasibility study for the 2021 Street Reconstruction Project, which consists of Drake Street, Perkins Lane, Bradford Street, and Gladview Lane.  The proposed scope of the project includes replacement of the water and sanitary sewer mains and services; curb and gutter; storm sewer; and new pavement.

Consistent with past projects, a portion of the costs associated with this work is proposed to be assessed to the benefiting properties.  Once the feasibility study is complete, the City will hold a public Improvement Hearing, at which time residents will have the opportunity to learn more about the project and provide feedback to the City Council.

The preliminary schedule for the project is as follows:

  • Complete Feasibility Study – January 2021
  • Public Hearing – February 22, 2021
  • Prepare Plans and Specifications – January to April 2021
  • Bid Opening - April 13, 2021
  • City Council Special Meeting to Review and Award Bid - April 14, 2021
  • Award Construction Contract – May 2021
  • Construction – June to September 2021

As we proceed through the process, additional project updates that more specifically address the schedule, construction methods, access during construction, and contact information for project personnel will be provided.  If you have questions or comments at this time, please contact the City Engineer, David Martini at david.martini@bolton-menk.com or 952-448-8838.

2021 Street Project Feasibility Report

2021 Street Project Presentation

Project Summary-FAQ.pdf 2021-07-16_Newsletter 5.pdf 

What's Under My Street.pdf

February 16, 2021 Virtual Open House    Access Passcode: K47P8V&w

February 22, 2021 Council Packet Items

April 27, 2021 Newsletter

June 14, 2021 Newsletter

July 1, 2021 Newsletter

July 9, 2021 Newsletter

July 16, 2021 Newsletter

July 23, 2021 Newsletter

July 30, 2021 Newsletter

August 6, 2021 Newsletter

August 13, 2021 Newsletter

August 20, 2021 Newsletter

August 27, 2021 Newsletter

September 3, 2021 Newsletter

September 10, 2021 Newsletter

September 17, 2021 Newsletter

September 24, 2021 Newsletter

October 1, 2021 Newsletter

October 8, 2021 Newsletter

October 15, 2021 Newsletter

October 22, 2021 Newsletter

October 29, 2021 Newsletter

November 5, 2021 Newsletter

November 12, 2021 Newsletter (final)

Weekly Updates

Sign up for weekly email updates by clicking here.


CodeRED

Sign up for CodeRED to receive timely messages about the project by clicking here.


Deferred Assessment Option - Qualified property owners may defer/postpone payment of special assessments based on age, income, disability, or military service. Payment will be due and payable in full at some future date. For each year the assessment is deferred, interest amounts are calculated and added to the total amount due.  See the Deferred Assessment Application for options and explanations.