2018 Street & Utility Improvements

Howard Avenue/Independence Street

Parkview Road/Maple Ridge Drive

Location

Howard Avenue from Drake St. to Main St. E.
and Independence St. from Howard Ave. to Baker Park Rd.

Location

Parkview Road from Amy Lane to Maple Ridge Drive and Maple Ridge Drive

Improvements

Street and storm sewer improvements include full reconstruction (existing street width) with new curb and gutter throughout the project area as well as the installation of storm sewer structures and piping.

Water main improvements include the removal of 6" cast iron and ductile iron pipes and replacing it with 8" PVC pipe.

Sanitary sewer improvements include removal the existing 8" clay sanitary sewer and replacing with 8" PVC pipe with the exception of lining a small section on Independence Street east of Perkins Lane.

Sidewalks or a bike path are not being constructed.

Improvements

  • Installation of draintile along east side of Parkview Road
  • Curb and gutter spot repairs as shown on plan page
  • Street and driveway patching as shown on plan page

Project Schedule*
Check Weekly Updates for most up-to-date information

Weeks of July 16 and July 23: Tree Removals
Week of August 6: Temporary water and street removals begin
Week of August 20: Sanitary sewer and watermain work begins
Week of September 17: Storm sewer work begins
Week of September 24: Begin street reconstruction
Weeks of Oct. 15 & Oct. 22: Restoration
June 2019: Final lift of asphalt placed

*Subject to Change

Project Schedule*
Check Weekly Updates for most up-to-date information

Week of October 8:

Draintile Installation and Curb and Gutter Spot Repair

Week of October 15:

Street and Driveway Patching

Week of October 22:

Restoration

*Subject to Change

Project Contacts

Project Contact Sheet (PDF)

Project Contacts

Project Contact Sheet (PDF)

Documents

Documents

Weekly Updates

Sign up for weekly email updates by clicking here.

November 16, 2018 Construction Update (PDF)

November 9, 2018 Construction Update (PDF)

November 2, 2018 Construction Update (PDF)

October 19, 2018 Construction Update (PDF)

October 12, 2018 Construction Update (PDF)

October 4, 2018 Construction Update (PDF)

September 28, 2018 Construction Update (PDF)

September 21, 2018 Construction Update (PDF)

September 14, 2018 Construction Update (PDF)

September 7, 2018 Construction Update- Additional Information (PDF)

September 7, 2018 Construction Update (PDF)

August 30, 2018 Construction Update (PDF)

August 24, 2018 Construction Update (PDF)

August 17, 2018 Construction Update (PDF)

August 10, 2018 Construction Update (PDF)